HOCON technologies received another contract for the layout planning of a climatic wind tunnel as part of the submission project (project site in China). A specification from the customer serves as the basis.

Facts:

  • 3D layout of the complete plant
  • Drafting of 2D drawings

aktuelle-projekte-hocon-3d-layoutplanung-klimawindkanal-1 aktuelle-projekte-hocon-3d-layoutplanung-klimawindkanal-2

Mission:

  • Clarifications with the customer
  • 3D planning of the wind tunnel and all adjacent buildings
  • Drafting of the 3D layout
  • 3D steel structure
  • 3D building construction